Memorial’s MUNnels: Why the Tunnels Need Repairs and What Is Planned

Memorial’s 2026 maintenance programme includes waterproofing and refurbishing nearly one kilometre of academic tunnels. The work is part of an eight-year infrastructure plan, not a declaration that the entire campus backlog is fixed. For daily travel, follow current campus signs and diversion notices.

In this story
A corridor in Memorial University’s St John’s tunnel system.
Memorial’s tunnel photograph published with its February 2026 infrastructure announcement. It does not certify which sections are currently open. Photo: Memorial University / Gazette; photographer not stated. Source.

The university beneath the university

Memorial has two versions of a winter journey between classes: the one exposed to St. John’s weather, and the one that passes beneath it. The MUNnels are academic tunnels, familiar enough to have their own nickname and enough shared history to feature in graduates’ complaints years after graduation.

Their appeal is easy to understand. A connecting route can make campus feel like one place rather than a series of separate battles with the forecast. When it leaks, looks tired or becomes difficult to use, the disappointment is about more than appearances. This is part of the university people actually move through, often several times a day.

The question in 2026 is what changes next. Memorial has announced a repair programme that specifically includes the tunnels. That is more concrete than another promise to improve campus life, but the details matter: which work is funded, why it takes time and what a finished repair will improve.

Source: Memorial: eight-year maintenance programme, February 2, 2026

Source: Residents discuss a 2026 photo tour of Memorial’s maintenance problems

Waterproofing comes before a prettier corridor

Memorial’s February 2 announcement describes re-waterproofing and interior refurbishment of nearly one kilometre of academic tunnels. The important pairing is work on the water problem and work inside. A fresh surface might improve how a corridor looks; it does not, by itself, explain whether the underlying cause of damage has been addressed.

There is a similar trap in judging a construction photograph. A stripped-back area can look worse while work is underway, and a tidy area can still conceal an unfinished problem. Ask what stage the work has reached before deciding that every exposed surface proves neglect or every new finish proves completion.

Students and graduates have supplied plenty of affectionate and less affectionate descriptions of the system. Some say they recognise conditions from their own much earlier years. That familiarity helps explain the impatience: the tunnels are not an abstract asset on a spreadsheet. They are a route people remember using with a backpack, a timetable and very little spare time.

Source: Memorial: eight-year maintenance programme, February 2, 2026

Source: Residents discuss a 2026 photo tour of Memorial’s maintenance problems

Source: Students joke about what grew on them at Memorial, April 2026

The larger eight-year plan

The tunnel work sits inside a broader programme approved by Memorial’s Board of Regents. Other announced components include elevator modernisation, building-envelope replacements, a primary data centre and demolition of Coughlan College. The programme also includes an emergency fund. It is a combination of access, building condition and the infrastructure needed to keep a university operating.

The February announcement linked the plan to $70 million over eight years from provincial relief on Core Science Facility debt. It also put deferred maintenance at $507 million at that time. Those figures show why one announcement should not be read as the disappearance of the whole backlog.

A backlog is work accumulated across assets; a programme is the work selected and funded over a particular period. Dividing one headline number by another will not tell a student whether a particular lift will work next week. Named projects, schedules and usable outcomes are a better way to follow progress.

Source: Memorial: eight-year maintenance programme, February 2, 2026

Source: Memorial: 2026–27 university budget

Why accountability needs more than a headline total

Arguments about maintenance often become arguments about executive pay, public funding and institutional priorities. Those are legitimate subjects. They are also different questions, and one large figure does not explain all of them. A budget line, a capital commitment and money available to fix a specific corridor should not be treated as interchangeable.

Memorial’s published response to its audit describes a Campus Renewal Committee and updated criteria for choosing physical and digital infrastructure work. That provides a route to more useful questions: how are projects prioritised, what access needs are considered and where can students see what has been completed?

The live Campus Renewal page redirected to a university service-interruption notice during our latest check. This guide therefore does not claim a newly verified project-by-project completion list. The February announcement establishes the programme; it does not establish which stretch is open or finished today.

Source: Memorial University: changes since the audit and campus renewal governance

Source: Memorial: current Campus Renewal Fee funding and projects

Using campus while renewal continues

For a class-to-class journey, use the latest campus information and signs, and leave a little time when your usual route changes. A general campus map identifies the university, not the open status of every tunnel connection. Someone who needs a step-free route should ask for a current route that meets that need rather than discovering an unsuitable diversion halfway through it.

If you are reporting a problem, name the location and what is happening. A leak, an access obstruction and a lighting fault require different responses. A clear description helps turn a familiar complaint into a specific job that can be tracked.

The best outcome will be pleasantly undramatic: a dry connection, a dependable route and fewer reasons to inspect the ceiling. Universities ought to give graduates enduring memories. Ideally, the unresolved leak should not be one of them.

Memorial University, St. John’s campus

230 Elizabeth Avenue, St. John's, Newfoundland and Labrador, Canada

Source: Memorial University: St. John’s campus contact address

Source: Memorial: eight-year maintenance programme, February 2, 2026

Source: Memorial University: St. John’s campus contact address

More place details

Source: Compare these places in Resources

Source: Residents discuss a 2026 photo tour of Memorial’s maintenance problems

Questions people ask

What are the MUNnels?

The nickname for Memorial’s academic tunnel connections on its St. John’s campus.

Source: Memorial: eight-year maintenance programme, February 2, 2026

Are repairs planned for Memorial’s tunnels?

Yes. The February 2026 programme includes re-waterproofing and interior refurbishment.

Source: Memorial: eight-year maintenance programme, February 2, 2026

How much tunnel is included in the announced work?

Nearly one kilometre of academic tunnels.

Source: Memorial: eight-year maintenance programme, February 2, 2026

How long is Memorial’s infrastructure programme?

The university announced an eight-year programme in February 2026.

Source: Memorial: eight-year maintenance programme, February 2, 2026

Does the plan include elevators?

Yes. Elevator modernisation and refurbishment are listed.

Source: Memorial: eight-year maintenance programme, February 2, 2026

What is building-envelope replacement?

Work on external elements such as windows, doors, brick and curtain walls, which the announcement includes.

Source: Memorial: eight-year maintenance programme, February 2, 2026

Does the programme mean all deferred maintenance is fixed?

No. Announcing a funded programme is different from completing the wider backlog.

Source: Memorial: eight-year maintenance programme, February 2, 2026

How large was the reported maintenance backlog?

The February 2026 announcement valued it at $507 million at that time.

Source: Memorial: eight-year maintenance programme, February 2, 2026

How do I check which MUNnel route is open today?

Follow current campus notices, signs and university directions for the journey. A general campus map does not establish the open status of each tunnel connection.

Source: Memorial University: St. John’s campus contact address

What should I check if I need a step-free campus route?

Ask the university for the current accessible route, including any construction diversions.

Source: Memorial: eight-year maintenance programme, February 2, 2026