Building permits for decks, fences and sheds in St. John's, Newfoundland and Labrador

St. John's, Newfoundland and Labrador, Canada

In St. John's you need a building permit before you build or change a deck, fence or shed. Fees start at $50 and minor work is usually issued in two to five days.

Key information

In St. John's you need a building permit before you add, replace, resize or move a deck, fence or shed. The fee is $9 per $1,000 of construction value with a $50 minimum, and minor work like fences is usually issued in two to five days.

Residential street with older houses and parked cars in St. John's
A residential street of older houses and parked cars in St. John's, June 2015. Photo: shankar s., Wikimedia Commons, CC BY 2.0.
On this page

At a glance

Deck, fence and shed permits in St. John's
ProjectForms to send with the building permit application
Deck (add, replace, resize or move)Deck Specifications Form and Deck Checklist
Fence (add, replace, change length or move)Fence Checklist
Shed or other accessory buildingAccessory Building Specifications Form and Accessory Building Checklist
Fee$9 per $1,000 of construction value, minimum $50
Usual time for minor work such as fencesTwo to five days
Permit Counter709-576-8565, permits@stjohns.ca

Sources: Building Permits | City of St. John's

When do I need a permit?

The City requires a permit for decks, fences, pools, new buildings, renovations, additions, driveways and other property improvements, among other work. The property owner must get the permit, even if a contractor does the work. The permit must be in hand before work starts.

Decks, fences and sheds each have their own checklist that goes with the application. A deck checklist is needed when you add, replace, resize or relocate a deck. A fence checklist is needed when you add, replace, change the length of or relocate a fence.

Sources: Building Permits | City of St. John's · Deck Checklist | City of St. John's · Fence Checklist | City of St. John's · Accessory Building Checklist | City of St. John's

How do I apply?

Fill in the Building Permit Application, a PDF form from the City, and attach the supporting documents. These can include plans and a survey. The documents you need depend on the work.

Building Inspection staff review the plans and check the work against the National Building Code, the St. John's Building By-Law and other rules. The building must be on a lot approved for its use and meet the setbacks for front, rear and side yards. It must also stay off easements.

Electrical and plumbing work need separate permits.

  1. Download the Building Permit Application and the checklist for your project.
  2. Add plans, a survey or site plan and the specification form if one is listed.
  3. Send the package to the Permit Counter.
  4. Wait for the permit before you start.

Sources: Building Permits | City of St. John's

What does it cost and how long does it take?

For fences, accessory buildings and other construction, the fee is based on estimated construction value. It is $9 per $1,000 up to $100,000, with a $50 minimum. Over $100,000, it is $9 per $1,000 for the first $100,000 plus $7.20 per $1,000 after that. The fee can be adjusted after the project if the final value is different.

Minor repairs such as siding, steps, fences, re-paving a driveway or exterior painting are usually issued in two to five days. Siding is excluded in Heritage Areas. No general time is given for other permits.

The Permit Counter is on the third floor of the John J. Murphy Building (City Hall Annex). Call 709-576-8565 or email permits@stjohns.ca. To pay a fee by phone, call 709-576-8694.

Sources: Building Permits | City of St. John's

Questions and answers

Do I need a permit for a fence in St. John's?

Yes. Adding, replacing, changing the length of or relocating a fence needs a building permit and the Fence Checklist.

Source: Fence Checklist | City of St. John's

Do I need a permit for a shed?

Yes. A shed is an accessory building. Send the Accessory Building Specifications Form and Accessory Building Checklist with the application.

Source: Accessory Building Checklist | City of St. John's

Do I need a permit for a deck?

Yes. Adding, replacing, resizing or relocating a deck needs the Deck Specifications Form and Deck Checklist.

Source: Deck Checklist | City of St. John's

Who must get the permit if I hire a contractor?

The property owner. The permit must be in hand before work begins.

Source: Building Permits | City of St. John's

How much is the permit fee?

$9 per $1,000 of construction value, with a $50 minimum, for work up to $100,000.

Source: Building Permits | City of St. John's

How long does a fence permit take?

Minor repairs such as fences are usually issued in two to five days.

Source: Building Permits | City of St. John's

Is the application online?

The application is a PDF form from the City's website.

Source: Building Permits | City of St. John's

Do I need other permits for electrical or plumbing work?

Yes. Electrical and plumbing work need separate permits.

Source: Building Permits | City of St. John's

Do setbacks apply to sheds and decks?

Buildings must meet zone setbacks for front, rear and side yards, and avoid easements.

Source: Building Permits | City of St. John's

Who do I call about a permit?

The Permit Counter at 709-576-8565 or permits@stjohns.ca.

Source: Building Permits | City of St. John's

Official service and next steps

Sources: Building Permits | City of St. John's · Application for Building Permit · Deck Checklist | City of St. John's · Fence Checklist | City of St. John's · Accessory Building Checklist | City of St. John's

Get in touch
My St. John’s

How can we help?